Scroll to top
Project Description

Induneil

Experience elevated living at Induneil, a premium project by the Rameshwaram Group. Thoughtfully designed spaces, quality construction, and peaceful surroundings come together to create a refined lifestyle.

Specification

  • Structure : R.C.C. column/beams slabs.
  • Walls : 8”/6”/4” thick external & 3”/4” thick internal partition walls, all internal walls and ceiling will have Plaster of Paris finish with a coat of cement primer and dry distemper over it.
  • Parking : Floor Chequered Tiles.
  • Toilets : Flooring in ceramic tiles and dado in ceramic tiles upto choukhat height. Basin with hot & cold mixture will be provided in both toilets.(Geysers not provided)
  • Electrification : Concealed copper wiring with standard make modular fittings and fixtures. Fan regulators, provision for AC point and T.V. & Telephone point in Drawing Room and all Bedrooms and intercom facility shall be provided (A.C., Fan, Tubelights not provided)
  • Floors : Vitrified/ceramic floor tiles in whole flat (Make size and quality as per discretion of the builder)
  • Doors : Wooden frame with flush/panel type shutters. Wooden/UPC door frames in Toilets. Ultra locking in main door and cylindrical lock in all bedrooms and toilet doors.
  • Windows : Three track sliding aluminum/UPVC windows with two track glazed and one track mosquito net provision.
  • Water Management : Connection from deep tube well to overhead tank connected with electric pump.
  • Sanitary Fittings : All C.P. or brass fittings of standard make. White glazed vitreous sanitaryware, cistern of white acrylic fibre glass. Hot and Cold provision in basin at Dining area with basin mixture.
  • Kitchen : All C.P. or brass fittings of standard make. Hot and cold provision.

Resources

RERA Details

  • Location : Kathal More
  • RERA No. : JHARERA/Project/42/2025
  • RERA Carpet Area : 1070 - 1200 Sq.Ft.
  • RERA Super Built Up Area : 1485 - 1660 Sq.Ft.
  • Status : Structure completed. Internal finishing in progress.
  • Possession Date : October 2026

On Map

Construction Updates

TOWER A

March 2025

Raft w/p – 100%

Raft/Pile cap – 100%

Stub col – 40%

Plinth Beam – 10%

TOWER B

April 2025

Raft w/p – 100%

Raft/Pile cap – 100%

Stub col – 40%

Plinth Beam – 10%

TOWER C

May 2025

Raft w/p – 100%

Raft/Pile cap – 100%

Stub col – 40%

Plinth Beam – 10%